Fisia Babcock Environment
Year: 2009
Location: Naples, Italy
Type of plant: MVA Neapel
Installation: Cold commissioning, hot commissioning, commissioning shift management
Location: Naples, Italy
Type of plant: MVA Neapel
Installation: Cold commissioning, hot commissioning, commissioning shift management
Hitachi Power Europe
Year: 2008-2009
Location: Boxberg, Germany
Type of plant: KW Boxberg
Installation: Loop checks, cold commissioning, hot commissioning and trial operation with commissioning shift management
Location: Boxberg, Germany
Type of plant: KW Boxberg
Installation: Loop checks, cold commissioning, hot commissioning and trial operation with commissioning shift management
Baumgarte Boiler Systems
Year: 2009
Location: Bitterfeld, Germany
Type of plant: Chemiepark Bitterfeld
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management
Location: Bitterfeld, Germany
Type of plant: Chemiepark Bitterfeld
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management
Baumgarte Boiler Systems
Year: 2009
Location: Frankfurt, Germany
Type of plant: AVA Nordweststadt
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management
Location: Frankfurt, Germany
Type of plant: AVA Nordweststadt
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management
Fisia Babcock Environment
Year: 2009
Location: Heringen, Germany
Type of plant: BKB Heringen
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management
Location: Heringen, Germany
Type of plant: BKB Heringen
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management
Fisia Babcock Environment
Year: 2008
Location: Shuaibah, Saudi Arabia
Type of plant: KW Shuaibah
Installation: Commissioning management
Location: Shuaibah, Saudi Arabia
Type of plant: KW Shuaibah
Installation: Commissioning management
WULFF Deutschland GmbH
Year: 2008
Location: Korbach, Germany
Type of plant: EBS Power station Korbach
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management
Location: Korbach, Germany
Type of plant: EBS Power station Korbach
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management
Hitachi Power Europe
Year: 2006-2008
Location: Ghent, Germany
Type of plant: BFG Ghent
Installation: Construction management, loop checks, cold commissioning, hot commissioning, commissioning shift management
Location: Ghent, Germany
Type of plant: BFG Ghent
Installation: Construction management, loop checks, cold commissioning, hot commissioning, commissioning shift management
Fisia Babcock Environment
Year: 2007-2008
Location: Herten, Germany
Type of plant: RZR Herten
Installation: Loop checks, cold commissioning, hot commissioning and trial operation with commissioning shift management
Location: Herten, Germany
Type of plant: RZR Herten
Installation: Loop checks, cold commissioning, hot commissioning and trial operation with commissioning shift management
ALSTOM Power Boiler Stuttgart
Year: 2004-2007
Location: Grevenbroich, Germany
Type of plant: KW Neurath BoA 2/3
Installation: Specialist construction management steel and pipeline construction, checking goods received
Location: Grevenbroich, Germany
Type of plant: KW Neurath BoA 2/3
Installation: Specialist construction management steel and pipeline construction, checking goods received
Standardkessel Duisburg
Year: 2007
Location: Hengelo, Netherlands
Type of plant: BEC Twence
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management
Location: Hengelo, Netherlands
Type of plant: BEC Twence
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management
AE&E Vienna/ A
Year: 2006-2007
Location: Vienna, Germany
Type of plant: Parent company
Installation: Assembly planning
Location: Vienna, Germany
Type of plant: Parent company
Installation: Assembly planning
Baumgarte Boiler Systems
Year: 2004-2005
Location: Frankfurt am Main, Germany
Type of plant: AVA Nordweststadt
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management
Location: Frankfurt am Main, Germany
Type of plant: AVA Nordweststadt
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management
Standardkessel Duisburg
Year: 2004-2005
Location: Lünen, Germany
Type of plant: BMK Lünen
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management
Location: Lünen, Germany
Type of plant: BMK Lünen
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management
Standardkessel Duisburg
Year: 2004
Location: Dunkerque, France
Type of plant: DK6 Dunkerque
Installation: Construction manager
Location: Dunkerque, France
Type of plant: DK6 Dunkerque
Installation: Construction manager
AE&E Lentjes Ratingen
Year: 2001-2003
Location: Frankfurt am Main, Germany
Type of plant: HKW Mainova
Installation: Construction management and commissioning management, loop checks, cold commissioning, hot commissioning and trial operation with commissioning shift management
Location: Frankfurt am Main, Germany
Type of plant: HKW Mainova
Installation: Construction management and commissioning management, loop checks, cold commissioning, hot commissioning and trial operation with commissioning shift management
Martin GmbH Munich
Year: 2002-2003
Location: Mainz Wiesbaden, Germany
Type of plant: MHKW Mainz
Installation: Project manager and commissioning group manager
Location: Mainz Wiesbaden, Germany
Type of plant: MHKW Mainz
Installation: Project manager and commissioning group manager
Lurgi Energie and Entsorgung Ratingen
Year: 2001-2002
Location: Maasvlakte, Netherlands
Type of plant: KW Maasvlakte
Installation: Health & safety plan, commissioning management and commissioning with cold commissioning, hot commissioning and trial operation.
Location: Maasvlakte, Netherlands
Type of plant: KW Maasvlakte
Installation: Health & safety plan, commissioning management and commissioning with cold commissioning, hot commissioning and trial operation.
Lurgi Entsorgung Ratingen
Year: 1998-1999
Location: Ratingen, Germany
Type of plant: Parent company
Installation: Design engineer
Location: Ratingen, Germany
Type of plant: Parent company
Installation: Design engineer
Steinmüller Gummersbach
Year: 1999
Location: Hamburg, Germany
Type of plant: MVA Hamburg Rugenberger Damm
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management
Location: Hamburg, Germany
Type of plant: MVA Hamburg Rugenberger Damm
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management
Lurgi Entsorgung Ratingen
Year: 1998-1999
Location: Hannover, Germany
Type of plant: Community power station Hannover
Installation: Quality assurance engineer, quality assurance at the subcontractors
Location: Hannover, Germany
Type of plant: Community power station Hannover
Installation: Quality assurance engineer, quality assurance at the subcontractors
von Roll Zürich
Year: 1998-1999
Location: Nuremburg, Germany
Type of plant: MVA TAN Nuremberg
Installation: Safety engineer
Location: Nuremburg, Germany
Type of plant: MVA TAN Nuremberg
Installation: Safety engineer
Lentjes Energietechnik Essen
Year: 1998-19999
Location: Düsseldorf, Germany
Type of plant: KW Lausward
Installation: Site management, commissioning management, commissioning, safety officer and health & safety coordinator Demolition of old boiler and construction of the new boilers.
Location: Düsseldorf, Germany
Type of plant: KW Lausward
Installation: Site management, commissioning management, commissioning, safety officer and health & safety coordinator Demolition of old boiler and construction of the new boilers.
von Roll Zürich
Year: 1997
Location: Velsen, Germany
Type of plant: AVA Velsen
Installation: Commissioning area management
Location: Velsen, Germany
Type of plant: AVA Velsen
Installation: Commissioning area management
BSR Berlin
Year: 1996-1997
Location: Berlin-Spandau, Germany
Type of plant: MVA-Ruhleben
Installation: Consultancy, commissioning
Location: Berlin-Spandau, Germany
Type of plant: MVA-Ruhleben
Installation: Consultancy, commissioning
Martin GmbH Munich
Year: 1997
Location: Twente-Hengelo, Netherlands
Type of plant: AVI Twente
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management
Location: Twente-Hengelo, Netherlands
Type of plant: AVI Twente
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management
ABB Turbinen Nuremberg
Year: 1996-1997
Location: Cologne, Germany
Type of plant: AVG Cologne
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management
Location: Cologne, Germany
Type of plant: AVG Cologne
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management
Eisenwerke Baumgarten Bielefeld
Year: 1995-1996
Location: Ulm, Germany
Type of plant: MHKW Ulm
Installation: Process engineering planning of the steam generator, commissioning and trial operation
Location: Ulm, Germany
Type of plant: MHKW Ulm
Installation: Process engineering planning of the steam generator, commissioning and trial operation
ABB PBS Brno / Czech Republic
Year: 1996
Location: Gera, Germany
Type of plant: HKW Gera
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management
Location: Gera, Germany
Type of plant: HKW Gera
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management
Eisenwerk Baumgarte
Year: 1996
Location: Iserlohn, Germany
Type of plant: MVA Iserlohn
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management
Location: Iserlohn, Germany
Type of plant: MVA Iserlohn
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management