Hitachi Power Europe
Year: 2008
Location: Soto / Spain, Germany
Type of plant: KW Soto, Ribera de Arriba
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management
Location: Soto / Spain, Germany
Type of plant: KW Soto, Ribera de Arriba
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management
Fisia Babcock Environment
Year: 2008
Location: Shuaibah, Saudi Arabia
Type of plant: KW Shuaibah
Installation: Commissioning management
Location: Shuaibah, Saudi Arabia
Type of plant: KW Shuaibah
Installation: Commissioning management
Fisia Babcock Environment
Year: 2008
Location: Geertruidenberg, Netherlands
Type of plant: Amer 9 Power Station
Installation: Commissioning management
Location: Geertruidenberg, Netherlands
Type of plant: Amer 9 Power Station
Installation: Commissioning management
AE&E Lentjes Ratingen
Year: 2004-2007
Location: Ferrybridge, Great Britain
Type of plant: KW Ferrybridge
Installation: Loop checks, cold commissioning, hot commissioning and trial operation with commissioning shift management
Location: Ferrybridge, Great Britain
Type of plant: KW Ferrybridge
Installation: Loop checks, cold commissioning, hot commissioning and trial operation with commissioning shift management
Hitachi Power Europe
Year: 2007
Location: Abono, Spain
Type of plant: Abono II
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management
Location: Abono, Spain
Type of plant: Abono II
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management
AE&E Lentjes Ratingen
Year: 2007
Location: Ankara, Turkey
Type of plant: KW Cayirhan
Installation: Commissioning management, commissioning with cold commissioning, hot commissioning and trial operation
Location: Ankara, Turkey
Type of plant: KW Cayirhan
Installation: Commissioning management, commissioning with cold commissioning, hot commissioning and trial operation
Fisia Babcock Environment
Year: 2007
Location: Rotterdam, Netherlands
Type of plant: KW Maasvlakte
Installation: Specialist construction management
Location: Rotterdam, Netherlands
Type of plant: KW Maasvlakte
Installation: Specialist construction management
LAB Group Stuttgart
Year: 2006
Location: Wels, Germany
Type of plant: WAV II Wels
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management
Location: Wels, Germany
Type of plant: WAV II Wels
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management
AE&E Lentjes Ratingen
Year: 2004-2006
Location: Yatagan / Milas, Turkey
Type of plant: KW Yatagan
Installation: Commissioning with cold commissioning, hot commissioning and trial operation
Location: Yatagan / Milas, Turkey
Type of plant: KW Yatagan
Installation: Commissioning with cold commissioning, hot commissioning and trial operation
AE&E Lentjes Ratingen
Year: 2002-2006
Location: Moneypoint, Ireland
Type of plant: KW Moneypoint, Kilrush
Installation: Loop checks, cold commissioning, hot commissioning and trial operation with commissioning shift management, Warranty
Location: Moneypoint, Ireland
Type of plant: KW Moneypoint, Kilrush
Installation: Loop checks, cold commissioning, hot commissioning and trial operation with commissioning shift management, Warranty
AE&E Lentjes Ratingen
Year: 2003
Location: Iskenderun, Turkey
Type of plant: KW Iskenderun
Installation: Commissioning management as well as cold commissioning, hot commissioning and trial operation with commissioning shift management
Location: Iskenderun, Turkey
Type of plant: KW Iskenderun
Installation: Commissioning management as well as cold commissioning, hot commissioning and trial operation with commissioning shift management
AE&E Lentjes Ratingen
Year: 1999-2003
Location: Frankfurt am Main, Germany
Type of plant: AVA Nordweststadt
Installation: Safety engineers, cold commissioning, hot commissioning and trial operation with commissioning shift management
Location: Frankfurt am Main, Germany
Type of plant: AVA Nordweststadt
Installation: Safety engineers, cold commissioning, hot commissioning and trial operation with commissioning shift management
Lurgi Lentjes Bischoff Essen
Year: 2002
Location: Almeria, Spain
Type of plant: KW Almeria
Installation: Recommissioning
Location: Almeria, Spain
Type of plant: KW Almeria
Installation: Recommissioning
Noell-KRC Würzburg
Year: 2001
Location: Würzburg, Germany
Type of plant: MHKW Würzburg
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management
Location: Würzburg, Germany
Type of plant: MHKW Würzburg
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management
Babcock Borsig Power Gummersbach
Year: 2000-2001
Location: Denmark, Denmark
Type of plant: KW Avedore / Denmark
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management
Location: Denmark, Denmark
Type of plant: KW Avedore / Denmark
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management
Noell-KRC Würzburg
Year: 2000
Location: Würzburg, Germany
Type of plant: MHKW Würzburg
Installation: Construction management
Location: Würzburg, Germany
Type of plant: MHKW Würzburg
Installation: Construction management
Lurgi Lentjes Bischoff Essen
Year: 1998-2000
Location: Yatagan / Milas, Turkey
Type of plant: KW Yatagan
Installation: Assembly monitoring and commissioning with cold commissioning, hot commissioning and trial operation
Location: Yatagan / Milas, Turkey
Type of plant: KW Yatagan
Installation: Assembly monitoring and commissioning with cold commissioning, hot commissioning and trial operation
Lurgi Lentjes Bischoff Essen
Year: 2000
Location: Ruternberg / Aschdod, Israel
Type of plant: KW Ruternberg
Installation: Coordination of the participating subcontractors for mounting of the internal fittings
Location: Ruternberg / Aschdod, Israel
Type of plant: KW Ruternberg
Installation: Coordination of the participating subcontractors for mounting of the internal fittings
Noell-KRC Würzburg
Year: 1999
Location: Schwarze Pumpe, Germany
Type of plant: KW Schwarze Pumpe
Installation: Dismantling
Location: Schwarze Pumpe, Germany
Type of plant: KW Schwarze Pumpe
Installation: Dismantling
Noell-KRC Würzburg
Year: 1998-1999
Location: Boxberg, Germany
Type of plant: KW Boxberg Werk IV
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management
Location: Boxberg, Germany
Type of plant: KW Boxberg Werk IV
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management
Lurgi Lentjes Bischoff Essen
Year: 1999
Location: Essen, Germany
Type of plant: Parent company
Installation: Quality assurance measure during the assembly
Location: Essen, Germany
Type of plant: Parent company
Installation: Quality assurance measure during the assembly
Noell-KRC Würzburg
Year: 1997-1998
Location: Megalopolis, Greece
Type of plant: PPC KW Megalopolis
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management
Location: Megalopolis, Greece
Type of plant: PPC KW Megalopolis
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management
Lurgi Lentjes Bischoff Essen
Year: 1996-1998
Location: Ankara, Turkey
Type of plant: KW Cayirhan
Installation: Project planning, construction management and commissioning with cold commissioning, hot commissioning and trial operation
Location: Ankara, Turkey
Type of plant: KW Cayirhan
Installation: Project planning, construction management and commissioning with cold commissioning, hot commissioning and trial operation
Noell-KRC Würzburg
Year: 1998
Location: Fürth, Germany
Type of plant: SBA ZAR Fürth
Installation: Commissioning group leader, cold commissioning, hot commissioning and trial operation with commissioning shift management
Location: Fürth, Germany
Type of plant: SBA ZAR Fürth
Installation: Commissioning group leader, cold commissioning, hot commissioning and trial operation with commissioning shift management
Noell-KRC Würzburg
Year: 1997
Location: Hamburg, Germany
Type of plant: HEW HKW Wedel
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management
Location: Hamburg, Germany
Type of plant: HEW HKW Wedel
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management
Noell-KRC Würzburg
Year: 1996-1997
Location: Iskenderun, Turkey
Type of plant: KW Iskenderun
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management
Location: Iskenderun, Turkey
Type of plant: KW Iskenderun
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management
Lurgi Lentjes Bischoff Essen
Year: 1996-1997
Location: Prague, Czech Republic
Type of plant: MVA Prague
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management and commissioning of the electrical and process control technology
Location: Prague, Czech Republic
Type of plant: MVA Prague
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management and commissioning of the electrical and process control technology
Noell-KRC Würzburg
Year: 1993-1996
Location: Schwarze Pumpe, Germany
Type of plant: KW Schwarze Pumpe
Installation: Commissioning shift manager, cold commissioning, hot commissioning and trial operation
Location: Schwarze Pumpe, Germany
Type of plant: KW Schwarze Pumpe
Installation: Commissioning shift manager, cold commissioning, hot commissioning and trial operation
von Roll Zürich
Year: 1995-1996
Location: Moerdijk, Netherlands
Type of plant: AZN / AVI Moerdijk
Installation: Commissioning shift manager, cold commissioning, hot commissioning and trial operation
Location: Moerdijk, Netherlands
Type of plant: AZN / AVI Moerdijk
Installation: Commissioning shift manager, cold commissioning, hot commissioning and trial operation
Noell-KRC Würzburg
Year: 1995-1996
Location: Chemnitz, Germany
Type of plant: HKW Chemnitz
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management
Location: Chemnitz, Germany
Type of plant: HKW Chemnitz
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management